• CATEGORIES
    • All Categories
    • Antiques
    • Art
    • Automotive
    • Baby
    • Beauty & Fragrances
    • Books & Magazines
    • Business & Industrial
    • Cameras & Photo
    • Cell Phones, PDAs & Accessories
    • Clothing & Shoes
    • Collectibles
    • Computers & Networking
    • Crafts
    • Electronics
    • Entertainment Memorabilia
    • Flowers & Gifts
    • Glass & Pottery
    • Health & Personal Care
    • Home & Garden
    • Jewelry & Watches
    • Misc
    • Movies & DVDs
    • Music
    • Office Supplies
    • Real Estate
    • Services
    • Sex Stuff
    • Sports & Outdoors
    • Sports Memorabilia
    • Tools & Hardware
    • Toys, Games & Hobbies
    • Video Games
  • COMMUNITY
  • FAQ
  • SELL
  • US
    • US
    • UK
    • AU
  • Cart
eCrater
  • Sign Up
  • Login
  • Home >
  • All Categories >
  • Books & Magazines >
  • eBooks(14564)
$18.00 Add to Cart

MGMT412 Unit 5 Assignment

MGMT412 Unit 5 Assignment

More than 10 available

Details

Shipping: US-Mainland: free (more destinations)

Condition: Used

Tweet    
  • Description
Mike was hired as a project manager to install hardwood floors for the company Awesome Floor and Tile. They will be installing new flooring into a local office building. Mike comes up with the list of work and estimates the time. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) are estimated in a given table. Following are the activities that are required to install the hardwood floor in the offices:
• Activity 1: Measure office room dimensions
• Activity 2: Estimate cost
• Activity 3: Material requisition
• Activity 4: Workforce requisition
• Activity 5: Special tool requisition
• Activity 6: Installation
• Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1.

Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2.

Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed.

The carpet installation project is complete after Activity 7 is completed.

Your assignment is to write a report that addresses the following:

If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities OT MT PT
Activity 1 2 3 4
Activity 2 3 6 9
Activity 3 4 8 12
Activity 4 6 8 10
Activity 5 8 10 12
Activity 6 10 14 18
Activity 7 4 6 8
You must also do the following:
• Determine and explain the expected completion time and the variance for each activity.
• Determine and explain the total project completion time and the critical path for the project.
• Determine and explain Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity.
• What is the probability that this project will be finished in 40 days or less? Explain.
• Define how to gather the project requirements.
• Analyze whether there are any potential changes that could impact overall project schedule and project finishing time.
• Explain the best methods for managing the change requests and what kind of process this project should involve.
• Analyze implications of changes in project scheduling.
• Explain the best methods for managing the change requests and what kind of process this project should involve.
• Evaluate applications of project management techniques in terms of the firm’s business operational goals and requirements

ANSWER WILL BE SENT BY EMAIL.
... [Full Description]

Title of Image

Seller Information

Seller

homework 5/5 Stars
  • Contact Seller
  • 96.53%, 4120 sales
‹ ›
View Store

Location

  • US, CA

Payment

  • Credit Cards
  • Credit Cards accepted via:
  • PayPal

Additional Info

  • About
  • Terms and Policy
  • Contact Info
  • FAQ
  • © 2026
  • ·
  • eCRATER
  • ·
  • Get your free online store
Last Updated: 6 Apr 2026 05:09:38 PDT
  • about
  • ·
  • terms
  • ·
  • privacy
  • ·
  • dmca
  • ·
  • contact
  • ·
  • news
Follow Us